top of page
  • Writer's picture Morningside Arena Media

Arena Extension Project Update

We have a roof!

The steel structure for both the new Arena entrance and building Extension Project is now largely complete by contractor B&E Boys with subcontractor Atlasco, with the cladding work on the roofs of both the Entrance and the Extension also complete. Below is the view from near the existing Arena Entrance on Charter Street.


Our partner, C3 Construction, have also completed the substructure and floor of the new Entrance, with the substructure for the new Extension Project to be finished upon completion of the floor. Work is also commencing on cladding the walls of both new Arena buildings.


The view from the new main Arena entrance on Memory Lane, and from the car park to the east of the Arena.

For more information about our expansion, how it fits into our aims for community development, and how we have funded the project, check out our article detailing the expansion project.

68 views0 comments

Recent Posts

See All

Morningside Arena Leicester welcomed the World Snooker Tour last week for the MrQ UK Championship qualifiers. The MrQ UK Championship is one of snooker’s most prestigious events, with a long history d

bottom of page